M
Missy
I have 'level Resource' turned on automatically.
Let's say John Smith completes Task 1 and only spent 10% of his work on it
(which makes him 90% available), and I assign John Smith Task 2 to work on
the same day that is estimated to take only 50% of his work. How do you get
Project to level John Smith to work on Task 2 on the same day as Task 1
without having to manually change the Work Unit to 50% yourself??? Is there a
setting or a check box i might have missed?
Thanks
Let's say John Smith completes Task 1 and only spent 10% of his work on it
(which makes him 90% available), and I assign John Smith Task 2 to work on
the same day that is estimated to take only 50% of his work. How do you get
Project to level John Smith to work on Task 2 on the same day as Task 1
without having to manually change the Work Unit to 50% yourself??? Is there a
setting or a check box i might have missed?
Thanks