R
Ranjana Mehta
Hi all:
We have been struggling with the reporting phase for Earned Value into
Project 2003. Our first and basic choice was to enter data manually (Physical
% complete, actual start and finish dates and actual hours) for the trial
project. This is expected to be entered by the task performers. But we want
to automate this in the near future as we move Earned Value to all projects
in the company.
Please let me know what variables CAN be imported to Project 2003. I know
that actual work and physical % complete fields can be imported from excel.
But how do we import the dates?
Thanks
Ranjana
We have been struggling with the reporting phase for Earned Value into
Project 2003. Our first and basic choice was to enter data manually (Physical
% complete, actual start and finish dates and actual hours) for the trial
project. This is expected to be entered by the task performers. But we want
to automate this in the near future as we move Earned Value to all projects
in the company.
Please let me know what variables CAN be imported to Project 2003. I know
that actual work and physical % complete fields can be imported from excel.
But how do we import the dates?
Thanks
Ranjana