baseline between projects

J

jgv2004

I apologize if this question has already been asked, but I have a schedule
with external dependencies. The question is, when I baseline this "master"
schedule, will the external schedules also be baselined?
Thanks for your help.
 
R

Rod Gill

Only information in the master schedule will be baselined. You have to open
the sub-projects separately to baseline them.
 