Baseline compare

B

Bobby McCally

I have received Project schedules. But, it does not appear they have created
baseline(s) nor statused the updates. Can I compare one updated schedule to
another, even if no baseline was created? I am most interested in gantt bar
comparison like one would do had a baeline been created.
 
C

Chris Marriott

Bobby

The baseline is the only comparison of the project schedule at the beginning
of the project unless you have another copy of the project plan. If you dont
then project copies the actual fields into the schedulefd fields or vice
versa depending on your tracking method

If you do have a copy of the original plan then use the compare projects
toolbar to check for variances

Hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 