Baseline plan

N

NewsGroup

I have saved a baseline for my project.
After that I have made some changes in my current schedule.
Is it possible to see my entire baseline project plan without any comparison
with current schedule?

Meena
 
J

Jan De Messemaeker

Hi,

In Tracking Gantt, Format, Bar Styles, set all "normal" bar styles to white.
HTH
 
N

NewsGroup

I do not want the baseline project plan in chart.
But I want it in the grid. (i.e)Spreadsheet view itself.

Meena.
 
J

Jan De Messemaeker

That is even easier, by insert column and delete (or hide) column you can
show baseline data and not show start and finish.
HTH
 
D

Dale Howard [MVP]

Meena --

Click View - Table - More Tables, select the Baseline table, and click
Apply. This will show you your baseline schedule and nothing else. Hope
this helps.
 