Hi,
I've just come across this and was wondering if it was a known bug.
I created a project baseline in Baseline1 so when I look at this in the
resource sheet view it has valid values and they are timephased in the
resource usage view.
However, after I save the schedule, closedown MS Project and reopen the
schedule all of the baseline1 information from the resource view is missing.
It is however still there in the timephased values in resource usage view.
I have tried this on other baselineX fields and the only one that is
retained is baseline
I have also tried this is Project Pro 2007 but the problem does not occur
there.
Thanks
I've just come across this and was wondering if it was a known bug.
I created a project baseline in Baseline1 so when I look at this in the
resource sheet view it has valid values and they are timephased in the
resource usage view.
However, after I save the schedule, closedown MS Project and reopen the
schedule all of the baseline1 information from the resource view is missing.
It is however still there in the timephased values in resource usage view.
I have tried this on other baselineX fields and the only one that is
retained is baseline
I have also tried this is Project Pro 2007 but the problem does not occur
there.
Thanks