Baseline Work

J

JJ

Why when looking at the resource usage screen with the Baseline Work Column
in the view, the sum of the total baseline for the resource is not calculated?
 
J

Jan De Messemaeker

Hi,

Just tried this in Project 2003 SP2, and the totals are there allright.
 
J

JulieS

Hello JJ,

I just ran a quick test, total baseline work shows in both the table
view (left side) and timescaled view (right side). Are you sure you are
showing Baseline Work not Baseline Budget Work?

I hope this helps. Let us know how you get along.

Julie