K
Kavey
I've been a trainer for MS Project for some years and have been able
to work, at a simple level, with resource calendars, with no
difficulties.
I have recently been upgrading my knowledge to vresion 2002 and
providing training to a new client.
As usual, when creating a new resource, a new calendar is created. I
then go into Change Working Time to make specific changes to that
calendar. However when I go to the Resource Sheet I am unable to
specify that the resource is working to their own calendar because it
is not listed in the relevant drop down.
What am I missing?
Thanks in advance for any advice.
Kavey
to work, at a simple level, with resource calendars, with no
difficulties.
I have recently been upgrading my knowledge to vresion 2002 and
providing training to a new client.
As usual, when creating a new resource, a new calendar is created. I
then go into Change Working Time to make specific changes to that
calendar. However when I go to the Resource Sheet I am unable to
specify that the resource is working to their own calendar because it
is not listed in the relevant drop down.
What am I missing?
Thanks in advance for any advice.
Kavey