M
Matium
Hi all,
I have a project manager assigned to the highest level summary task for
my project, as he will be needed until the project finish. Is this good
pratice or what is the best way to monitor how his work will increase
if there is delays and the project gets extended?
I have a project manager assigned to the highest level summary task for
my project, as he will be needed until the project finish. Is this good
pratice or what is the best way to monitor how his work will increase
if there is delays and the project gets extended?