T
tom
I am creating a strucutre in Project and want to track the following
task
planned and actual start date
planned and actual finish date
total work effort (not duration) - although I will show the duration based
on the plan start and finish dates
work remaining in hours
% complete
resources and predecesors and other misc info.
I would like to manually ENTER all of the DATES and would like to be able to
adjust the work remaining or % complete fields without having any dates
change. What are the best fields to use and other setup options to make this
happen?
Currently, I am using START and FINISH as my Plan dates, WORK as my total
work estimate (in hours), REMAINING WORK as my remaining hours or estimate to
complete and ACTUAL START and ACTUAL FINISH to capture when the tasks do in
fact start or finish. However, I seem to have issues with dates when I
adjust % complete. Any help would be appreciated.
task
planned and actual start date
planned and actual finish date
total work effort (not duration) - although I will show the duration based
on the plan start and finish dates
work remaining in hours
% complete
resources and predecesors and other misc info.
I would like to manually ENTER all of the DATES and would like to be able to
adjust the work remaining or % complete fields without having any dates
change. What are the best fields to use and other setup options to make this
happen?
Currently, I am using START and FINISH as my Plan dates, WORK as my total
work estimate (in hours), REMAINING WORK as my remaining hours or estimate to
complete and ACTUAL START and ACTUAL FINISH to capture when the tasks do in
fact start or finish. However, I seem to have issues with dates when I
adjust % complete. Any help would be appreciated.