best way to enter data

M

Markarina

When using fixed units tasks, is their a preferred way to enter data,
data being work, resources.

Is it better to enter work first then resources or resources then
work, ideally what I want to end up with is having every task have
it's resource allocated at 100% unless max units in resource sheet is
set to a lower figure. so that all task are completed in the shortest
possible time.

Thanks

Mark
 
J

Jim Aksel

I do it by Window/Split.
I type the resource name, or use the drop down, in the bottom pane. I enter
the work for each resource, then hit OK. Duration becomes a calculated
field. Note the default is Fixed Units/Effort Driven. You can learn more
about that in the help
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
M

Mike Glen

Hi Markarina ,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #5 & 10 on entering resources, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 