Blue check mark showing for task with Remaining Work hours

B

Blake 20

Problem: The PWA Timesheet view is showing a check mark indicator for
completion for task while there still are remaining hours for the resource in
the .mpp file (PRO).

What Happen? The resource ran out or hours and the task did roll off the
Current Task view in PWA. However, I realized that I needed to add more hours
so I increased the 0 remaining work hours to XX for the resource because this
is an operational project that is on going throughout the year.

Thereafter I republished the assignments (did not work) and then I tried
publishing all information. No avail.

My goal is to get task(s) showing back into the PWA Resource Timesheet,
Current Task view and have the blue check mark indicator removed.

Thank you!

I already visited http://www.mvps.org/project/faqs.htm for the FAQs. No
information there pertains to this issue, but thank you in advance.
 
M

Mike Glen

Hi Blake 20,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
B

Blake 20

Mike, I am not understanding your intent, please read the bottom of my first
letter.
 
M

Mike Glen

Hi Blake 20,

If you read the FAQ you will see that for questions relating to problems
with Project being used on a server, the correct newsgroup where the experts
hang out is the microsoft.public.project.server newsgroup. Try posting your
query there.

Mike Glen
Project MVP
 