break in task bar with different resource allotments

R

redlurered

Hello,
I have created a task bar with breaks in it . I would like a resource to
have different percentage of time allocated to the same task, in the
different broken sections. Is this possible?
 
J

Jan De Messemaeker

Hi
Yes, but it is umpteen times more elegant to make it several tasks.
By all means, in the Task Usage View you can neter hours planned by day.
HTH
 
M

Mike Glen

Hi redlurered ,

Welcome to this Microsoft Project newsgroup :)

You could use the Resource Usage view and type in the Work hours you want
when the resource is available.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP