B
Balroc
I'm trying to define a task that can occur in a wide time window relative to
the work effort involved. Let's say that I have a design spec that's
drafted and then sent out for review. The review period is 30 days and I
want to assign tasks for people to read the spec and approve or deny it.
There's 3 people and I want to assign them each a task with a 1/2 day
duration to do this action, but I don't care when they do so in the 30 day
review period. If I set up the task with a .5d duration and start/end dates
that are 30 days apart, project will either change the start/end dates or
increase the duration. How can I get past this?
TIA
the work effort involved. Let's say that I have a design spec that's
drafted and then sent out for review. The review period is 30 days and I
want to assign tasks for people to read the spec and approve or deny it.
There's 3 people and I want to assign them each a task with a 1/2 day
duration to do this action, but I don't care when they do so in the 30 day
review period. If I set up the task with a .5d duration and start/end dates
that are 30 days apart, project will either change the start/end dates or
increase the duration. How can I get past this?
TIA