Can I change the default calander that Project opens a new project with? I
know I can create a new calander in project, but I don't seem to be able to
change the default and have project use the calander I created to open a new
project. I know this sounds stupid but I am importing 100's of small projects
with a baseline created in excel by addition formulas. When I import the file
to a new project file it compensates for week end days and adds to my task
start and finish, but as you know the baseline fields are not caalulated
fields in project, so they don't change with the start and finish dates. This
throws my baseline off from my task. Any ideas?
know I can create a new calander in project, but I don't seem to be able to
change the default and have project use the calander I created to open a new
project. I know this sounds stupid but I am importing 100's of small projects
with a baseline created in excel by addition formulas. When I import the file
to a new project file it compensates for week end days and adds to my task
start and finish, but as you know the baseline fields are not caalulated
fields in project, so they don't change with the start and finish dates. This
throws my baseline off from my task. Any ideas?