L
labrach
Hi all
The work column gives the total work of a task/project (work between
start and finish date)
I would be able to calculate the current work of a Project (work
between the start date and a current/given date)
This is very usefull when trying to report on cost by month for
example
Is that possible ??
thanks
labrach
The work column gives the total work of a task/project (work between
start and finish date)
I would be able to calculate the current work of a Project (work
between the start date and a current/given date)
This is very usefull when trying to report on cost by month for
example
Is that possible ??
thanks
labrach