N
Niklas
Hi
I think I have tried all possible ways doing this calculation, but I think I
have missed something....
I have a task which will I have estimted to be 200 hours. I have 3 resources
which are availeble. Resource1 = 65%, resource2 = 50% and resourse3 = 25%. I
also know the start date. By enetering this date I want MsPropject2003 to
calculate duration, 200/(6.5+5+2.5) = 14.29 days, and give each resource
their part of the work each day (Resourse1 = 6.5 hours/day etc, the last day
will bee evenly distributed). How do I do it?
regards
/Niklas
I think I have tried all possible ways doing this calculation, but I think I
have missed something....
I have a task which will I have estimted to be 200 hours. I have 3 resources
which are availeble. Resource1 = 65%, resource2 = 50% and resourse3 = 25%. I
also know the start date. By enetering this date I want MsPropject2003 to
calculate duration, 200/(6.5+5+2.5) = 14.29 days, and give each resource
their part of the work each day (Resourse1 = 6.5 hours/day etc, the last day
will bee evenly distributed). How do I do it?
regards
/Niklas