A
Anita
If I have a task that is 6 days with two people doing it, I add two people
and it changes the number of days to 4.5 (when I choose the smart tage
option), I thought it would change it to 3 (double the people, half the time)
- I know that's probably the same as
saying effort driven, but I adjusted it using the smart tag option. Just
can't see why it has changed to 4.5 from 6. Can you shed any light? (default
task type is fixed duration)
Thanks
v2003
and it changes the number of days to 4.5 (when I choose the smart tage
option), I thought it would change it to 3 (double the people, half the time)
- I know that's probably the same as
saying effort driven, but I adjusted it using the smart tag option. Just
can't see why it has changed to 4.5 from 6. Can you shed any light? (default
task type is fixed duration)
Thanks
v2003