G
Glenn
Hi all,
I am incorporating a cost estimate that I have successfully imported to
Project from Excel. I have one field named "Daily Output" and another named
"Quantity". Both are Number fields as Number1 and Number2 respectively. If
I have a Daily Output of 100 and my Quantity is 1000, then I should provide a
Duration of 10 days, if the task is not split. Can I have Project take the
values in these two fields and calculate the duration?
This post is also in the Project Developer area. Hope this is OK. Please
advise if not.
thanks,
glenn
I am incorporating a cost estimate that I have successfully imported to
Project from Excel. I have one field named "Daily Output" and another named
"Quantity". Both are Number fields as Number1 and Number2 respectively. If
I have a Daily Output of 100 and my Quantity is 1000, then I should provide a
Duration of 10 days, if the task is not split. Can I have Project take the
values in these two fields and calculate the duration?
This post is also in the Project Developer area. Hope this is OK. Please
advise if not.
thanks,
glenn