S
Stevan
Hi!
I would like to planned and actual activity percent completion. I do not
want to add any resources. Is it possible to get palnned percent completion
just based on activity duration, so we can find out how many percent of each
activity should be completed each week.
Thanks,
Stevan
I would like to planned and actual activity percent completion. I do not
want to add any resources. Is it possible to get palnned percent completion
just based on activity duration, so we can find out how many percent of each
activity should be completed each week.
Thanks,
Stevan