W
W mather
I have a rolled-up task where the calculated total for Work is double the
actual sum of the sub-tasks. Is there a way to fix this without deleting the
sub-tasks and re-adding them. I am using Project Standard 2002 with SP1.
actual sum of the sub-tasks. Is there a way to fix this without deleting the
sub-tasks and re-adding them. I am using Project Standard 2002 with SP1.