Birmangirl
....sadly I can't be too detailed: I've been sent a PDF of a Gantt chart. One
task has a start & finish date of 31 July/11 September. Assuming a 5-day
working week, the duration is 30 days. The plan has been baselined and this
task shows a BL Early Start of 19 June and a BL Early Finish of 7 July.
Question 1: Why is the BL duration so much shorter, and
Question 2: I have a Baseline Variance of -45 days. Presumably, this
indicates that the scheduled work is less than originally planned. Why is it
as much as 45 days?
Apologies for my ignorance, but I'm not convinced that the person sending me
the PDF fully understands what they are doing (and neither am I).
TIA
Amanda
task has a start & finish date of 31 July/11 September. Assuming a 5-day
working week, the duration is 30 days. The plan has been baselined and this
task shows a BL Early Start of 19 June and a BL Early Finish of 7 July.
Question 1: Why is the BL duration so much shorter, and
Question 2: I have a Baseline Variance of -45 days. Presumably, this
indicates that the scheduled work is less than originally planned. Why is it
as much as 45 days?
Apologies for my ignorance, but I'm not convinced that the person sending me
the PDF fully understands what they are doing (and neither am I).
TIA
Amanda