Calendar changes not reflected in Task Finish dates

P

Paul

HELP ! I'm really stuck, having sold my company on using Resources in Project
to successfully plan.

I'm passed the delivery hour for this plan, and I am stuck.

Instead of adding more resources to a project , I want to add an extra hour
of workday to all resource people. So I created a new base Calendar called
Rush and used the wizard to change the work times in it. All people have the
calendar now assigned to them.

Why isn't this changing the finish dates ???
 
P

Paul

OK, I found my own answer: it IS updating, but the changes did not make
enough difference to cause the finish DAY to change.
 
M

Mike Glen

Hi Paul,

Welcome to this Microsoft Project newsgroup :)

Also, you might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 