Calendar - day 1, day 2 etc

D

DW

Hello
I teach MS project and I have a simple question that is so simple I cannot
find the answer.

How do I set the task calendar to "days". Day 1, day 2 etc. For students
new to Project it's easier to start this way and then move on to dates.

Kind regards.........David in France
 
J

JulieS

Hi Dave,

You can change the timescale to show different labels including D1, D2,
etc. Try the Format > Timescale menu and change the labels on the bottom
tier as you need.

The date format choices in the table views (left side of the gantt
chart) can be modified through Tools > Options, View tab. There is not
an option for showing D1, D2 etc. in the date format.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top