K
Kenny Anderson
Hello again,
I have tasks that are based on calendar days, rather than working days.
(e.g. to fulfill federal requirements, a public hearing must be advertised a
30 day minimum before the hearing date) However, most of my tasks are based
on the work week, so it doesn't make sense to change my default calendar.
One way that I can alter this is to assign the task to a different resource
and give that resource a 7-day work week, rather than 5. Is there another
way to do this or have I found the best option?
TIA,
Kenny Anderson
I have tasks that are based on calendar days, rather than working days.
(e.g. to fulfill federal requirements, a public hearing must be advertised a
30 day minimum before the hearing date) However, most of my tasks are based
on the work week, so it doesn't make sense to change my default calendar.
One way that I can alter this is to assign the task to a different resource
and give that resource a 7-day work week, rather than 5. Is there another
way to do this or have I found the best option?
TIA,
Kenny Anderson