P
pratta
Dear All
Running a resource pool across a number of projects, I am using a calendar
the copy of Standard. When I change the standard hours from 8:00 to 12:00 and
1:00 to 5:00, (to say 7 hours and start at 9:00am) ., the calendar now shows
the new times as "nondefault working time". Should not this be the "Default"
working time for the new calendar?
How do I make a non 8 hour day the "Default" working time, in this regard.
If I change the calendar during the life of the project, what impact does it
have on project history, and is there any danger in doing so?
Kind Regards.........
Pratta
Melbourne.
Running a resource pool across a number of projects, I am using a calendar
the copy of Standard. When I change the standard hours from 8:00 to 12:00 and
1:00 to 5:00, (to say 7 hours and start at 9:00am) ., the calendar now shows
the new times as "nondefault working time". Should not this be the "Default"
working time for the new calendar?
How do I make a non 8 hour day the "Default" working time, in this regard.
If I change the calendar during the life of the project, what impact does it
have on project history, and is there any danger in doing so?
Kind Regards.........
Pratta
Melbourne.