I want to put stat holidays into my project (which is Project Pro 2003,
running on Project Server 2003, by the way).

But, when I go into Tools | Change Working Times, and select "Standard
(Project Calendar)" in the top combo box, the right side of the dialog box
("Set selected date(s) to:" section) is all disabled. I am an Administrator
of Project, with full access to the PWA. But I can't find any setting
anywhere that will enable this section of the dialog box. How do I change the
Nonworking time?

Thanks for your help
 
D

Dave

I just discovered the answer to my own question. If anybody is having the
same problem, here's your answer:

When running Project under Server, you cannot directly update working time.
An Administrator level user has to do it in the Enterprise Global.

The Administrator clicks Tools | Enterprise Options | OPen Entrprise Global.

This opens a separate project. Now they can select Tools | Change Working
Time, make the necessary changes to the dates, and then save and exit out of
this project.

The new non-working dates should now be in your Project.
 
M

Mike Glen

Hi Dave,

Thanks for the feedback. Next time you might like to try posting on the
server newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs,
companion products and other useful Project information can be seen at this
web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top