Dave
I want to put stat holidays into my project (which is Project Pro 2003,
running on Project Server 2003, by the way).
But, when I go into Tools | Change Working Times, and select "Standard
(Project Calendar)" in the top combo box, the right side of the dialog box
("Set selected date(s) to:" section) is all disabled. I am an Administrator
of Project, with full access to the PWA. But I can't find any setting
anywhere that will enable this section of the dialog box. How do I change the
Nonworking time?
Thanks for your help