sonali
resource is simultaneously working on 2 projects for 2 hrs daily, where as
I being the project manager would like to give him
specific timing for each project.
Eg.
a.. On project A he is working daily 10 am to 12 pm, on Project B he is
working daily from 4 pm to 6 pm,
b.. I want to set a calendar for him which will be for the specific time.
c.. One option can be using a standard calendar else preparing a calendar
for Mon to Sat giving the specific time, like
Mon - Sat 10 am to 12 pm or Mon-Sat 2 pm to 4 pm
If we allocate these calendars, Resource Pool shows the resource is over
allocated, where as he is not, as we are using him for 4
hrs in different time slot even though the days are same.how to resolve
this problem?
I being the project manager would like to give him
specific timing for each project.
Eg.
a.. On project A he is working daily 10 am to 12 pm, on Project B he is
working daily from 4 pm to 6 pm,
b.. I want to set a calendar for him which will be for the specific time.
c.. One option can be using a standard calendar else preparing a calendar
for Mon to Sat giving the specific time, like
Mon - Sat 10 am to 12 pm or Mon-Sat 2 pm to 4 pm
If we allocate these calendars, Resource Pool shows the resource is over
allocated, where as he is not, as we are using him for 4
hrs in different time slot even though the days are same.how to resolve
this problem?