One of my resources comes in every Thursday and Friday for about a year. I
am assigning him 40% on the projects he is assigned to. But is there a better
method so that Project (2003) knows that his resource calendar has
non-working days on Mon, Tue, Wed, Sat, and Sundays?
Regards,
Dip