In the calendar view only tasks (and not summary tasks) are shown by
default.

Therefore, to show the various sub-tasks within a regular summary task or
or the sub-tasks within a "summary task for a recurring task" you must
expand those tasks in the Gantt display. After they have been expanded in
the Gantt view you will see them in the Calendar view.



Hello,

How can I see a recurrence tasks at the Calendar View ?

Thanks

Pnina



--
 