R
rfreschner
I've set the default calendar in my Project 2007 project to a 6 hour day for
internal resources and when I enter 6 hours, duration equals 1 day. I've
added another calendar for Consultant resources that I've set working times
to 8 hour days. How do I get the duration to equal 1 day for these resources
when I enter 8 hours - right now it continues to use the 6 hour day.
internal resources and when I enter 6 hours, duration equals 1 day. I've
added another calendar for Consultant resources that I've set working times
to 8 hour days. How do I get the duration to equal 1 day for these resources
when I enter 8 hours - right now it continues to use the 6 hour day.