C
Chachi
I mostly use fixed duration tasks and have noticed that project struggles
with calculating work and or duration when I use calendars. I have setup a
project calendar and associated resource calendars and seem to be able to
confuse project fairly easily if the resource calendar's base calendar does
not match the project's base calendar. If I add in task calendars it seems
to further complicate the matter. So, I guess my question is...are calendars
really intended to be used when you have mostly/all fixed duration tasks?
Any tips I should be aware of when using calendars?
Thanks for any info you can share.
with calculating work and or duration when I use calendars. I have setup a
project calendar and associated resource calendars and seem to be able to
confuse project fairly easily if the resource calendar's base calendar does
not match the project's base calendar. If I add in task calendars it seems
to further complicate the matter. So, I guess my question is...are calendars
really intended to be used when you have mostly/all fixed duration tasks?
Any tips I should be aware of when using calendars?
Thanks for any info you can share.