Garold said:
Looking to create a critical path flowchart and text in Project 2003. Any one
got an ideal how to do that? Any help is a appreciated.
Garold,
In the scheduling world a flowchart is referred to as a network diagram
and yes, Project can create graphical representations other than a Gantt
chart. Take a look at the views: Descriptive Network Diagram, Network
Diagram and Relationship Diagram. Each offers a slightly different "cut"
of the data and they can be customized, although Project does not have
as much flexibility with its graphics as some other applications (e.g.
Visio) or add-ons to Project (e.g. Milestones).
Hope this helps.
John
Project MVP