S
scabHead
I am really struggling with the Fixed Unit vs Fixed Duration vs effort driven
type stuff. The projects I manage have several tasks. I want to be able to
assign and change resources without having any durations changed or any other
weird stuff happen. My work consists of mainly assigning inanimate resources
likes rooms, forklifts, tables, chairs, phones, etc. The task shouldn't get
shorter or longer if I add or remove a phone.
I have been assigning resources to a hammock task so that they span a whole
period of sub tasks. Everything seems to work fine. Then I look at task
usage view and some of the resources do not span the entire duration of the
hammock task. This doesn't make any sense to me. I think Project is trying
to do some math here but I don't want it to.
If anyone can tell me the simplest way to do what i am trying to do I would
really appreciate it.
type stuff. The projects I manage have several tasks. I want to be able to
assign and change resources without having any durations changed or any other
weird stuff happen. My work consists of mainly assigning inanimate resources
likes rooms, forklifts, tables, chairs, phones, etc. The task shouldn't get
shorter or longer if I add or remove a phone.
I have been assigning resources to a hammock task so that they span a whole
period of sub tasks. Everything seems to work fine. Then I look at task
usage view and some of the resources do not span the entire duration of the
hammock task. This doesn't make any sense to me. I think Project is trying
to do some math here but I don't want it to.
If anyone can tell me the simplest way to do what i am trying to do I would
really appreciate it.