D
doniy
I have several tasks (Piling). I have 10 rigs for these tasks to complete
3000 piles.
I want to use rig as resource, and assign it to those tasks,then leveling.
But if I use work resource, the work can only be count in hours, not No. of
piles.
Need I convert No. of piles to hours?
If I use material resource, it can't be leveled.
How to solve this problem?
Thanks in advance.
3000 piles.
I want to use rig as resource, and assign it to those tasks,then leveling.
But if I use work resource, the work can only be count in hours, not No. of
piles.
Need I convert No. of piles to hours?
If I use material resource, it can't be leveled.
How to solve this problem?
Thanks in advance.