Can resource leveling solve this problem?

D

doniy

I have several tasks (Piling). I have 10 rigs for these tasks to complete
3000 piles.
I want to use rig as resource, and assign it to those tasks,then leveling.
But if I use work resource, the work can only be count in hours, not No. of
piles.
Need I convert No. of piles to hours?
If I use material resource, it can't be leveled.

How to solve this problem?
Thanks in advance.
 
D

DavidC

Think of the piling as taking a certain duration. Presumably you intend
making a number of tasks to cover various groupings of piles, then each group
will have a duration to complete that task. Assign the number of rigs to the
task and when complete then level on the rig resource. If you have an
overallocation of rigs at any time then project will shift tasks to level out
that resource as long as there are no other constraints.

Hope this helps

DavidC
 