In the project, click File - Page Setup. Click the Legend tab and then
click the Left tab in the Alignment section. Edit or enter Legend info in
any of the three tabs. Hope this helps.
Actually that is the text we wanted to modify, i.e., instead of just
"Milestone" change it to state what type of Milestone — "Delivery milestone."
Is there anyway of updating that?
Thanks for the replies so far!
Yes. Just create you own in the Format/Bars dialog. You might like to see
FAQ Item: 31 on customising task bars. FAQs, companion products and other
useful Project information can be seen at this web
address:http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
Project MVP