E
Elvis
Hi,
I am a relatively new user of project. I have created 30 individual tasks
that all follow one another by date so for example.. if task 1 starts on the
3rd....and runs for 4 days it will end on the 6th...the 7th will be a new
task. If I change the start date on task 1 how do I get the rest of the dates
to automatically change to reflect the new start date?
Thanking You
Elvis
I am a relatively new user of project. I have created 30 individual tasks
that all follow one another by date so for example.. if task 1 starts on the
3rd....and runs for 4 days it will end on the 6th...the 7th will be a new
task. If I change the start date on task 1 how do I get the rest of the dates
to automatically change to reflect the new start date?
Thanking You
Elvis