change subtasks to tasks

J

Jeremy

I created an outline and want to change it by moving a subtask back to a
higher level, but when I click on the subtask and then click the "Outdent"
arrow, nothing happens.
 
J

Jeremy

Hi Julie:

I just checked and it seems I already have SP-2, but the problem still exists.

Any other suggestions?

Thanks for your help.
Jeremy
 
J

JulieS

Hi Jeremy,

You're welcome and thanks for the feedback.

As to the ongoing problem: Is your project sorted? Try sorting by ID
(Project > Sort > By ID) and see if you can outdent.

HTH
Julie
 
J

JulieS

Hi Jeremy,

You're welcome. If the re-sort doesn't fix the problem, let us know.

Julie
 
J

Jeremy

Julie:

It still doesn't outdent after sorting by ID (actually, it was already
sorted by WBS code, which provides the same sort order). In any case, I've
decided to just work with it as is and change the task names to make it more
accurate, so it's not as much of a problem as before. Still, it would be nice
to be able to do this in future when a workaround might not be as convenient.

Thanks again.

Jeremy
 
J

JulieS

Hi Jeremy,

It sounds as though there may be a problem with your file if you cannot
still outdent.

If you would like, you may email me the file and I'll take a peek.

My email address is:
passport 6847 at maine rr com

remove the spaces and convert the at to an @.

Julie
 