Change symbol on all milestone tasks?

K

Kris R.

How do I change the symbol on milestones, from the default black diamond, to
something else, on ALL milestone tasks on ALL projects?

I assume I do something in the Enterprise Global, but I don't know where.

Thanks,

Kris R.
 
J

JackD

Here is what you do:

Format menu,
Barstyles
choose the milestone line and change it to what you want.

For the enterprise, I'm not 100% sure as I don't use it, but I think you
need to check out the enterprise global before you do this and make sure you
are in the default view (Gantt view or something like that).
 
K

Kris R.

Yup! You were right - check out enterprise global and do it that way.

Doh! Must be a Monday...!

Thanks!
 