See embedded ...
scott_hanebutt said:
I agree with you in almost all cases (there are a very few specific cases I
am not sure about). I was actually more interested in knowing how to
change
it to the night shift, and just put down 24hr because I didn't think it
effected my question.
One example of a 24 hr callendar I can think of is: You have three guys
each working a different shift in 24/7 environment. They are the only
people
involved in the project and they have the same skill set. In this case I
think a 24hr calender would be more acurate. You would of course assign a
different callendar to each resource to reflect thier individual shifts.
I'm not sure that the 24 calendar would actually be best there. My 3
resources are Joe Day, Bill Swing, and Fred Grave. I have task X to do that
will require 24 man-hours of work to complete. I have several options when
I assign the resource to the task, depending on the needs of my project. I
can assign one of those resources to it, I can assign 2 of them, or I can
assign all three. The 24-hour calendar assumes you will always assign all
three. With the Project calendar set to a normal generic workday for a
single resource, when I enter the task it will show up with timing as if one
resource was going to do it which is the normal level to take the work
breakdown to. That 24 man-hours task will take 3 workdays and the only
thing that changes with my choice of which resource to assign is the time it
starts on the first workday. If I need it done sooner I can add one or both
of the renmaining resources. If my Project Calendar is the normal day shift
calendar, Joe's base calendar is the same, Bill's is an added swing shift
base calendar and Fred's the night shift calendar, I get accurate scheduling
regardless of the way I choose to assign the workers.
Another situaltion would be if you have 24/7 production with 20 on 1st, 10
on 2nd, and 10 on 3rd. Each shift has aproximatly the same skill set. A
normal task could then be worked on for an average of 16 hours a day. 8
on
1st, and another 8 on either 2nd or 3rd. In this case it may be better to
use an 16hr base callendar.
Not sure about that example either but have to think on it a bit before
commenting.