Hi koolkat ,
Welcome to this Microsoft Project newsgroup
This sounds most odd! Why change the calendar if you don't want the dates
to change? If you're wanting to enter new tasks then create a new calendar
with Sat & Sun working, and assign the tasks to use that calendar. Note
that this is not suitable for human resources as I presume they would like
their week ends free. Also, I get the impression that you have entered the
dates? If so, you are really affecting the flexibility of Project, as
entering dates will cause constraints. Try entering Tasks, Durations,
Precedences and Resources and then let Project do what it was designed for -
to give you a schedule of what is possible with the data you've entered.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for my free Project Tutorials