A
Anders The Sheep
We utilise Project Server and time periods with non-working plans including
lines for Holiday. A team member put 7 hours on each day during w/c 12.Sep (a
future period) through PWA timesheet, the manager then accepted this, no
problem.
However holiday plans changed and the user cleared out the hours and
re-submitted, to their manager, who approved and republished. When looking
through the users PWA timesheet no time is shown, when looking at the
non-working plan they are still shown as being on holiday (7hours each day).
The impact here is when re-planning this resource is not available for that
week when they should be.
Any ideas, on what we might have done wrong or how we can fix?
lines for Holiday. A team member put 7 hours on each day during w/c 12.Sep (a
future period) through PWA timesheet, the manager then accepted this, no
problem.
However holiday plans changed and the user cleared out the hours and
re-submitted, to their manager, who approved and republished. When looking
through the users PWA timesheet no time is shown, when looking at the
non-working plan they are still shown as being on holiday (7hours each day).
The impact here is when re-planning this resource is not available for that
week when they should be.
Any ideas, on what we might have done wrong or how we can fix?