Hi,
Being a (lousy) golfer myself, I coudn't help adding my 2cts worth here.
Technically speaking, what you need is a task calendar.
Go to Tools, Change Working time
New
Name: Seven days (or any )
Click the hedings of Sat and Sun
Nonstandard working time
OK
Now select the two follow-up tasks
Task Information icon
Advanced
Calendar, select 7 days
That is what you look for.
But one thing bothers me in your post.
How are you going to use this to "measure success of the operation"??
Curious about that...
Keep the swing going.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Dale said:
John-
Thanks for getting back to me. My project is not heavy on management.
Actually, my project is an assignment to management (my project team) and
they are involving front line people in just two tasks in support of their
management effort. Maybe sharing my real scenario with you and others will
be helpful.
The project is a pilot project to see if we want to install a GPS system
on our golf carts at our 27 hole golf course. It is being set up as a 60 day
pilot project to test our customer's response to using this "value added"
service. Management has the tasks of researching various systems and
vendors, doing site visits to other facilities, bidding a system, selecting
a system, installing a system, setting up training for front line staff in
the use of the system, surveying the customers and then writing a report and
recommendation on the results of the pilot test. They will do all of that
work M - F from 8:00 until 5:00 (management has a 5 day work week).
Two of the sub-tasks, however, are the actual selling of the value added
service to the customers by the front desk staff (which happens 7 days per
week- we operate our golf course all 7 days- management just works 5 of
those days), and the actual 60 day piloting of the GPS system by our
golfers. As it turns out, I'm not really assigning "resources" to those two
sub-tasks [selling the program and allowing the golfers to use the value
added service]. Management is not involved in that. Front desk staff is.
And maybe that is my problem. I want to measure the success (or failure)
of what is happening in both periods (thus my reason for having them in my
project plan), but maybe I can't do that. Or do you think I can?
Actually, I posed my question incorrectly in my first posting. My question
really should be, can I have 16 sub-tasks be set up on a 5 day work week,
and 2 of my sub-task set up on a 7 day work week?
Thanks for giving this some thought. By the way, I did use the Calendar
tab- Help button, and there were no answers for this question (which I
probably asked wrong the first time). It did, however, lead me to the
on-line web site, and thus my posting in this Discussion group area.