AntonioR20 said:
I am trying to change the default working time for all new projects.
Currently, the default is 8:00 - 5:00 p.m. I would like to change that to
8:30 - 5:00 p.m.
I've already tried to change the time in Tools_Options, but it does not
change the time when I go into the calendar. I am having to go into "Change
working times" and doing it from there each time.
AntonionR20,
The option to "use default" on the "Change Working TIme" window is
misleading. As the help file says, checking the "use default" option
"Resets the selected working and nonworking days you selected to match
the settings on the selected resource's base calendar." It does NOT set
the working time calendar to match the default start and stop times
under Tools/Option/Calendar tab.
If you want to set up your working times to be 8:30 to 12:30 and 1:00 to
5:00 then you will need to do it in both places. To make it easier in
the Change Working TIme window, I suggest you create your own custom
calendar (it may or may be helpful to start with the Standard calendar).
Then select the headers (i.e. M-F) for whatever month is currently
showing (that will effectively select all working days for every month).
Then check "Non-default working time" and set your times. That custom
calendar will only be active for the file where it was created but it
can be moved to your Global (thus making it available to any Project
file) by using Tools/Organizer.
Hope this helps.
John
Project MVP