Changing resoource % does not change duration?

J

Joe

I have added a task and assigned a resource. Now, I have changed the %
available of this resource, but it will not adjust the duration. I
have the task set for fixed units. Any clues? It was working, but now
it seems it ignores the % available. Thanks.
 
J

Jan De Messemaeker

Haven't you changed the %complete? Complete tasks aren't recalculated.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top