Changing resource availability %

L

Lauchlan M

Hi,

Say I have a resource, available 100%, and I allocate the resource to a
number of tasks.

I then edit the resource from the resource sheet, and make the resource
available only for 50%.

I then want to keep the amount of work the same, and have Project
recalculate all durations for tasks this resource was allocated to.

However, Project does not seem to recalculate for new tasks.

What's the best way to accomplish the change?

Thx,

Lauchlan M
 
J

Jan De Messemaeker

Hi,

Filter for the task using this resource
Open the resource assignment window
select the resoruces
Click Replace
Enter the sme resopurc name but with 50%
OK
 