Changing the Calendar

W

wendy2of3

I have Project 2003 Pro and I would like to only show the work days in the
Calendar. I would like the non-work days to not show on any of the
calendars or reports or printouts. I am trying to have the work week start
on Thursday and end on Wednesday showing the work days only so I don’t have
two blank days taking up space on the printouts.

Also can you tell it how many days you want on the printout of the gantt
chart, as it is only showing three days. I would like to show the 5 day work
week.

Thanks
 
J

JackD

Sorry. Your wish is not granted.
Maybe in the next version.
A lot of people have been rubbing that lamp and wishing on that star.
 
J

JulieD

Hi

as Jack said - the first is not possible, however to attempt to answer your
second question - either choose format / timescale and set the timescale so
you can see each day (or however you want) - or if that is not the problem,
try file / print and have a look at the timescale options there - change it
to ALL if it is only showing a date range.

Cheers
JulieD
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top