D
DaveFusion
In my plan I allocate resource always at a % of 60, the other 40 is to cover
contingency and ad-hoc unplanned tasks.
In order to accelerate the plan I want to change this to 80%, is there any
'quick' way of doing this ?
The only way I could think of was from the gnatt using the 'split' screen
and changing the work units for each resource on each task ( which will
probably take about a week !).
I was hoping perhaps to use the resource usage view and just scroll down and
change the % for each task per resource - but the work field doesn't show.
contingency and ad-hoc unplanned tasks.
In order to accelerate the plan I want to change this to 80%, is there any
'quick' way of doing this ?
The only way I could think of was from the gnatt using the 'split' screen
and changing the work units for each resource on each task ( which will
probably take about a week !).
I was hoping perhaps to use the resource usage view and just scroll down and
change the % for each task per resource - but the work field doesn't show.