Changing work Times

O

omar

As a project manager, how can I change working times for a resource?
I go to TOOLS>CHANGE WORKING TIME....I click on the resource and it gives me
an error that I dont have the right permission.
 
D

Dale Howard [MVP]

Omar --

If you are using Project Server 2002 or 2003, you cannot change the working
time for resources unless you are a Project Server administrator. To do so,
the Project Server must check out the resource in the Enterprise Resource
Pool, double-click the resource, select the Working Time tab, and enter the
nonworking time on the resource's calendar. Hope this helps.
 
M

Mike Glen

Hi Omar,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top