choosing an early critical path

C

csmith6

I have a project where I ship to a customer in the middle of the project and
would like to calculate the critical path for that ship date and not the end
of the project. Is there a way to do this?
 
J

Jan De Messemaeker

Hi,

On the shipping put a deadline equal to its expected finish date
On the end task put a deadline later than its expected finish date (not in
P2007)
Hoep this helps
 